BRINGUP: consolidate the outstanding bench validations into Next work
This commit is contained in:
@@ -2206,3 +2206,52 @@ accordingly ("Automatic — AP country, else World").
|
||||
position preserved; a resume waypoint with the latch locked stays
|
||||
laser-less; `laser_latch=0` written mid-ramp does not re-arm FIRE
|
||||
(probe the PSU-connector LASER_ON line as in `fire_test.py`).
|
||||
**The GATE A part of this list is DONE (K1/K2/K3 + `fire_test`
|
||||
A/B/U pass on image `20260814223300`, campaign record above); the
|
||||
platform-hygiene items themselves are consolidated in item 10.**
|
||||
10. **Outstanding bench validations (consolidated 2026-08-15).** Every
|
||||
safety-critical drill is done: GATE A (K1/K2/K3, `fire_test` A/B/U),
|
||||
GATE B (auth/CSRF/loopback/settings-flood probes), dry motion and
|
||||
dead-man drills (SIGKILL reap+safing, SIGSTOP → underrun, restart
|
||||
mid-move, no stray fd), the X-2 flood, and the live-fire set (A-1
|
||||
emission witness, A-5 HV telemetry, X-3 job-based disarm, G-10
|
||||
grace-in-Hold, A-2 lid-IR first look). What has **not** been run on
|
||||
hardware, none of it gating, in rough priority order:
|
||||
- **Lid-IR fire characterization at cutting power** — ≥3
|
||||
representative jobs at real power, read the per-job baseline/peak
|
||||
log lines, set `cool_fire_ir_delta` well above the worst normal-cut
|
||||
peak (never below ~15 counts), keep watch-only until several jobs
|
||||
show no false trip, then enable the fire-abort gate. The 40 % cut
|
||||
moved the channels only ~+3 counts, so the gate ships 0.
|
||||
- **Kernel platform-hygiene batch (item 9), on the flashed image:**
|
||||
panic mid-motion with motors locked and the laser latched (motion
|
||||
stops, safety lines read safe); decay mode set/readback per axis;
|
||||
LED behavior and a clean module unload; the two new probe lines in
|
||||
dmesg with no bank warnings; a dead-man trip with the head
|
||||
registers read back (measure laser off, UV LED off, lens motor
|
||||
de-energized). Plus the Phase 8 trio: load/unload under
|
||||
`CONFIG_DEBUG_MUTEXES` (needs a debug kernel build), a forced
|
||||
`-EPROBE_DEFER` unwind, and a concurrent `cat` of a state attr
|
||||
during `rmmod`.
|
||||
- **Dead-man collateral:** a kernel dead-man trip leaves the pump and
|
||||
airflow running (heat sources only go off); kill forgectrl during
|
||||
an update download (no pinned device, no EBUSY respawn storm);
|
||||
re-run the armed kill drill on the *expected*-stop path (mode
|
||||
switch / diag suspend) on the current image.
|
||||
- **Physical-evidence negatives:** force a head I²C error and confirm
|
||||
the witnesses report an error, not a plausible value; confirm a
|
||||
failed head capture leaves the measure laser off.
|
||||
- **Cloud mode:** the C-1 cancel-with-a-rejected-settings-action
|
||||
drill (cancel must stop the cut); malformed-frame and DNS-blip
|
||||
injections against a live session; the oversize/bad-header job
|
||||
rejected before the ring loads (tracked in `CLOUD.md`); re-verify
|
||||
the homing accelerometer motion-window counts against the
|
||||
characterized thresholds at the next live homing (the witness now
|
||||
samples at ~100 Hz); confirm a real print header's fan duties
|
||||
round-trip to the engine (item 8).
|
||||
- **Opportunistic:** `STATE_FAULT` recovery via `enable` without a
|
||||
module reload the next time a DRV8825 fault line actually trips.
|
||||
- **Config-dependent, deliberately not gated:** an armed GRBL job
|
||||
after an underrun cuts at the stale origin unless homing is
|
||||
required (GRBL mode permits unhomed cutting; the underrun itself
|
||||
alarms and unlinks the anchor).
|
||||
|
||||