ScottW514 54d238d67d Record the campaign behind a print longer than the ring
The work ran from 2026-08-18 to 2026-08-20 and is finished, so the plan it ran
from is retired the way plans are retired here: what is durable moved into the
documents that describe the present, and the dated record of how the result was
obtained lands here.

The entry keeps the parts that live nowhere else. That the campaign started
from a wrong belief and was corrected by the factory itself, which stages a job
into its ring in free-checked segments and then appends to it for as long as
the job lasts. That the proof was already on the machine, a 107 MB job played
through a 32 MiB ring in this board's own factory logs. The two defects the
building surfaced, a dry ring reporting success and a pause that could not
retrace on a streamed job. And what it cost to be sure: a decoder 41 times too
slow to keep a ring fed, which only showed itself against a real 53 MB job.